The Enhanced Growth Credit Program can play a vital role in the planning of new and expanding businesses, particularly for those operations in which electric power is a major component in the cost of the final product. It can be vital because the program could represent a substantial economic advantage to your company in today's fierce competitive climate.

TO QUALIFY

The Minimum Added Load Requirement to Qualify Depends on Your Classification:

SIC* Qualifiers (New or Expansion)
Must add a minimum of 100 kW
Mining (SIC's 10-14)
Manufacturing (SIC's 20-39)
Bulk Transportation (SIC's 40, 42, 44, & 45)
*Standard Industrial Code

All Electric Qualifiers (New or Expansion)
Must add a minimum of 250 kW
Commercial and Industrial customers that are all electric on HVAC with more
than 50 percent of floor space heated and cooled. HVAC,interior lighting, and
cooking must represent 50 percent or more of customer's rated electric load.

Other Qualifying Customers (Expansions Only)
Must add a minimum of 250 kW
Commercial and Industrial customers that expand by at least 250 kW of
electric heating and cooling, electric water heating, and/or electric cooking.

If You Qualify, CPWS Offers the Following Credit Options:

CREDIT PER ADDED FIRM KW

Six Year Credit Option

Four Year Credit Option

       
Year 1 
  $6.00
Year 1 
  $6.00
Year 2 
  $5.25
Year 2 
  $6.00
Year 3 
  $4.50
Year 3 
  $6.00
Year 4 
  $3.75
Year 4
$6.00
Year 5 
  $3.00
   
Year 6 
  $2.25
   
Year 7
$1.50
   
Year 8
$0.75
   