- Developer must submit a master plan and phasing plans.
- Power Engineering will lay out the development, take CPWS system phase balance into consideration while designing.
- Engineer will estimate the construction cost associated with the facility infrastructure and determine the contribution-in-aid (CIA) required for the development.
- Developer must sign an agreement with CPWS indicating the developer desires CPWS to extend electrical facilities.
- Developer must pay any required aid-in-construction amount and install facilities before CPWS will begin construction.
- Developer to furnish and install all raceways as applicable.
- Developer to furnish and install any needed equipment and transformer pads.
- CPWS Engineering shall inspect underground customer supplied system prior to the ditches being back filled and the concrete pad forms before pouring.
- Engineer will draft the work order for the project.
- Work order is issued to Power Construction for the installation of needed facilities.